Nordic Mining Q1 2025 presentation: First garnet shipment amid production ramp-up challenges

Published 21/05/2025, 07:04
Nordic Mining Q1 2025 presentation: First garnet shipment amid production ramp-up challenges

Introduction & Market Context

Nordic Mining ASA (OB:NOM) presented its Q1 2025 interim results on May 21, highlighting both progress and challenges as the company transitions from construction to production at its flagship Engebø Rutile and Garnet project. The Norwegian mineral developer completed construction and entered the ramp-up phase in January 2025, marking a significant milestone in the company’s development.

Despite achieving its first commercial garnet shipment in May, Nordic Mining acknowledged operational challenges with slurry pump design that have delayed the company’s production ramp-up by approximately two quarters. The stock closed at NOK 20.85 on May 20, down 1.65% ahead of the presentation.

Quarterly Performance Highlights

Nordic Mining reported a profit of NOK 22 million for Q1 2025, though this figure was heavily influenced by currency fluctuations rather than operational performance. The company’s financial results reflect its transition from project phase to operational P&L starting February 1, 2025.

Key operational achievements during the quarter included the completion of construction activities and the successful mining of approximately 570,000 tons of rock. The company also secured additional financing through a USD 33 million bond tap issue, creating financial runway for the extended ramp-up period.

The most significant milestone came shortly after the quarter ended, with the company’s first commercial shipment of 569 tons of garnet dispatched on May 12, destined for the Barton Group’s Rotterdam facility.

Operational Progress and Challenges

Nordic Mining’s production ramp-up has been hampered by design issues in the pump circuits, which the company has been working to resolve. A remedial solution installed in March did not deliver the expected results, prompting the company to contract an external party to review the plant design.

The company reported that prioritized pumps were modified in May with performance now meeting expectations. Production of rutile is expected to commence at the end of May, with a planned maintenance and modification stop scheduled for July to address the remaining pumps.

As shown in the following production ramp-up chart, Nordic Mining is targeting an annual production rate by the end of 2025 of 235,000 tons of rutile and 35,000 tons of garnet. The company emphasized that while the ramp-up delays have deferred revenue streams by approximately two quarters, long-term production levels remain unchanged.

Mining operations have progressed well, with access to high-grade ore secured months ahead of schedule. Approximately 1 million tons of rock have been transported to the deposit area since the start of mining operations, with a focus on optimizing machinery utilization planned for the second half of 2025.

The company has also maintained its environmental commitments, with a seven-member team monitoring regulatory requirements and environmental impacts. No deviations or breaches of permits have been registered, and all monitoring results have been communicated to regulatory bodies and the local community.

Financial Analysis

Nordic Mining’s financial position reflects both the challenges of the production ramp-up and the company’s efforts to secure adequate funding. The cash flow statement for Q1 2025 shows an opening balance of NOK 467 million, with operating activities consuming NOK 25 million and investing activities requiring NOK 110 million. The USD 33 million bond tap issue provided net proceeds of NOK 349 million, contributing to a closing cash balance of NOK 636 million.

The company’s profit and loss statement shows an operating loss of NOK 78.1 million, driven by production expenses of NOK 35.5 million, depreciation and amortization of NOK 19.8 million, and other operating expenses of NOK 15.2 million. However, a net exchange rate gain of NOK 115.2 million, primarily due to USD weakening against NOK, resulted in a profit before tax of NOK 22.0 million.

Nordic Mining’s balance sheet shows a combined carried amount of producing mine, property, plant and equipment, and intangible assets of NOK 2.8 billion as of Q1 2025. With a cash balance of NOK 617 million and an equity ratio of 41%, the company appears to have sufficient financial resources to navigate the extended ramp-up period.

Forward-Looking Statements

Nordic Mining remains committed to reaching stable production at design capacity for both rutile and garnet by year-end 2025, despite the current challenges. The company plans its first rutile shipment in the third quarter of 2025, following the successful garnet shipment in May.

The appointment of a new Chief Commercial Officer, set to start on July 1, 2025, signals the company’s shift in focus from construction to commercial operations. Management emphasized their focus on maintaining the quality of mineral concentrates during the ramp-up phase, recognizing that product quality will be critical for long-term market success.

While the production delays represent a setback for Nordic Mining, the successful resolution of the pump design issues and the completion of the first commercial garnet shipment demonstrate progress toward full-scale operations at the Engebø project. Investors will be watching closely to see if the company can meet its revised timeline for achieving stable production by the end of 2025.

Full presentation:

This article was generated with the support of AI and reviewed by an editor. For more information see our T&C.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers
© 2007-2025 - Fusion Media Limited. All Rights Reserved.