Bitdeer Technologies Group (BTDR) reported a 35% increase in self-mining hashrate to 22.3 EH/s in July 2025, driven by continued deployment of its SEALMINER mining rigs. The company self-mined 282 Bitcoins during the month, representing a 39% increase from June 2025.
The Singapore-based Bitcoin mining company energized an additional 159 MW of electrical capacity across its operations in Bhutan and Norway during July. The company also completed its 100 MW hydro-cooling conversion at its Rockdale, Texas facility.
Bitdeer manufactured 21.2 EH/s worth of SEALMINER A2 mining rigs, with 5.9 EH/s shipped to external customers and 10.2 EH/s deployed for self-mining operations. An additional 4.8 EH/s of mining rigs are currently in transit to company sites in Norway and Bhutan.
The company’s total hashrate under management reached 36.4 EH/s in July, up from 30.6 EH/s in June. Bitdeer managed 213,000 mining rigs during the period, including 127,000 self-owned units.
Infrastructure development continued across multiple locations. The Tydal, Norway site now has 126 MW online with the remaining 49 MW expected to be energized by the end of Q3 2025. In Bhutan, the Jigmeling facility has 235 MW online, with 265 MW expected to come online in phases by Q3 2025.
The Massillon, Ohio project timeline has been adjusted to Q1 2026 completion due to transformer delivery delays and labor shortages. The company expects 21 MW to be energized by October 2025, with the remaining 200 MW following in phases.
Bitdeer’s total available electrical capacity now stands at 1,257 MW globally, with an additional 1,433 MW in the pipeline across various development stages.